'''The FloFlo'''
 
 
The [https://www.youtube.com/watch?v=wUJ-GnuNP14 FloFlo] is an ancient drilling tool, modernised by dutchman Floris de Vos in 2011 (see [https://www.facebook.com/FLOFLONL/ Facebook page])
 
The FloFlo employs a hoist using a three legged tower. The drillbit is repeatedly hoisted and released to pulvarise the hard soil as it hits the ground. Once a substantial amount of soil has been pulvarised, the drillbit is replaced by the bailer, equiped with a valve, to pull out the soil. Thus it is a manpower driven drill tool. Anyone can do it, and it is cheap and efficient.
 
 
 
[[Image:01-FloFlo-c.jpg|thumb|left| The floFlo tower]]
 
[[Image:01-FloFlo-c.jpg|thumb|left| The floFlo tower]]
 
[[Image:01-FloFlo-a.jpg|thumb|right| Bringing it on]]
 
[[Image:01-FloFlo-a.jpg|thumb|right| Bringing it on]]
Line 25: Line 18:
 
[[Image:12-Queen.jpg|thumb|right| Queen and odikro visiting drill site]]
 
[[Image:12-Queen.jpg|thumb|right| Queen and odikro visiting drill site]]
 
[[Image:13-Odikro.jpg|thumb|left| Odikro inspects the drilling]]
 
[[Image:13-Odikro.jpg|thumb|left| Odikro inspects the drilling]]
 +
 +
EcoSan Ghana drilled for water [https://www.google.com/maps/place/6%C2%B009'05.5%22N+2%C2%B008'59.8%22W/@6.151543,-2.1521287,17z/data=!3m1!4b1!4m5!3m4!1s0x0:0x0!8m2!3d6.151543!4d-2.14994?hl=en in front of a primary school in Modaso] (Diaso), Ghana, using a FloFlo drill tower (percussion drilling).
 +
 +
.
 +
 +
'''The FloFlo'''
 +
 +
The [https://www.youtube.com/watch?v=wUJ-GnuNP14 FloFlo] is an ancient drilling tool, modernised by dutchman Floris de Vos in 2011 (see [https://www.facebook.com/FLOFLONL/ Facebook page])
 +
The FloFlo employs a hoist using a three legged tower. The drillbit is repeatedly hoisted and released to pulvarise the hard soil as it hits the ground. Once a substantial amount of soil has been pulvarised, the drillbit is replaced by the bailer, equiped with a valve, to pull out the soil. Thus it is a manpower driven drill tool. Anyone can do it, and it is cheap and efficient.
  
 
.  
 
.  

Revision as of 19:20, 8 September 2016

The primary school in Modaso
Queen Nana Adjei Maanu
The FloFlo
The floFlo tower
Bringing it on
Drilling crew in full gear
The crew
The drill bit in action
In full swing
In full swing
Lunchtime
drill hole
broken bit holder
fixed bit holder
fixed bit holder attached
fixed bit holder attached
Queen and odikro visiting drill site
Odikro inspects the drilling

EcoSan Ghana drilled for water in front of a primary school in Modaso (Diaso), Ghana, using a FloFlo drill tower (percussion drilling).

.

The FloFlo

The FloFlo is an ancient drilling tool, modernised by dutchman Floris de Vos in 2011 (see Facebook page) The FloFlo employs a hoist using a three legged tower. The drillbit is repeatedly hoisted and released to pulvarise the hard soil as it hits the ground. Once a substantial amount of soil has been pulvarised, the drillbit is replaced by the bailer, equiped with a valve, to pull out the soil. Thus it is a manpower driven drill tool. Anyone can do it, and it is cheap and efficient.

.

The First Phase

Drilling started on August 16, 2016. Then on August 19 the kit holder got loose, which was fixed on august 20. On august 22 the drilling resumed. On September 2, the queen Nana Adjei Maanu and the odikro (elder of the village) stopped by for some encouraging words. That very same day, after 13 days of drilling, water was found, at 50 feet depth.

.

The Second Phase

In the second phase, the pipes and the pump need to be installed. When two different contractors from nearby towns were asked for an estimate, they however charged us too much money (17.490 and 8.000 cedi respectively), so that we first need to buy the needed materials ourselves. We promised the queen that we would definitely return to finish our work there.

.

The Costs of the First Phase

It took 13 days of drilling. Each person was paid 50 cedi per day. So, 5 x 50 x 13 = 3250 cedi in total (which was about 740 euro at the time). Plus 50 cedi for fixing the bit holder. Plus transportation costs for the project manager and the floflo; 190 cedi. 10 cedi for a torchlight. 80 cedi for caution tape. Plus 150 cedi in total for the water used in the drill hole. 50 cedi for gloves. total costs: 3780 cedi. (860 euro)